See below
Design
See below
Construction
Summer 2025
Completion
$7.1M
Project Cost
About this Project
To enhance campus safety for all community members and visitors, UC Davis is upgrading security infrastructure with additional cameras, emergency call boxes, and outdoor lighting. Seven new emergency call boxes—providing instant connection to 911 dispatchers—will be installed on the Vet Med campus and along bike paths. Additionally, 11 new security cameras will be placed in key locations, including intersections along La Rue Road, Hutchison Drive, Old Davis Road, and near select Egghead sculptures. Lastly, seven areas will receive new groups of outdoor lights along pedestrian pathways to improve visibility and safety.
- Emergency Call Box Progress
Location
Status
Completion
Sprocket Bikeway Construction 8/2025 Soccer Bikeway at Mann Lab Construction 8/2025 Physical Sciences Mall near the Silo South Construction 8/2025 Hutchison Drive at Bioletti Way Construction 8/2025 Dairy Road at Dairy Bikeway Construction 8/2025 Pritchard Veterinary Medicine Teaching Hospital Construction 8/2025 Tupper Hall Construction 8/2025 - Security Camera Progress
Location
Status
Completion
"Eye on Mrak," north of Mrak Hall Installed 5/2024 "See No Evil, Hear No Evil," Mrak Hall Circle Installed 5/2024 "Stargazer," North Hall Construction 8/2025 Garrod Drive at Environmental Services Lane Construction 8/2025 Garrod Drive at La Rue Road Construction 8/2025 Hutchison Drive Roundabout at West Village Construction 8/2025 Hutchison Drive at Health Sciences Drive Construction 8/2025 La Rue Road at Hutchison Drive Construction 8/2025 La Rue Road at Segundo Services Administration Construction 8/2025 Old Davis Road at Hutchison Drive Construction 8/2025 South Gate at Old Davis Road Construction 8/2025 - Outdoor Lighting Progress
Location
Status
Completion
Cushing Way from Hutchison Drive to Lot 6 Design 12/2025 Olson Hall Bike Parking and East Quad Bikeway Design 12/2025 Peter J Shields Avenue from California Avenue to A Street Design 12/2025 South Core Campus Neighborhood near the Art Building, Music Building, Wright Hall walkways and the plaza between School of Education and Olson Hall Design 12/2025 Hutchison Drive from Bioletti Way to the Teaching & Learning Complex Design 12/2025 Lot 25 South Pedestrian Pathway along Dobbins Field and the Aggie Soccer Field Design 12/2025 Sprocket Bikeway from California Avenue to the Housing Admin Building roundabout Design 12/2025
Learn more about ongoing security improvements
More information

UC Davis Invests in Additional Security Improvements
Read more about the $20 million campus investment made toward improving campus security in the next five years
Client | UC Davis Police Department |
Design Team | Catalyst Security Consulting, Edge Electrical Consulting, Cunningham Civil Engineering, Bevier Structural Engineering |
Contractor | TBD |