International Center

Rendering of Eastern View of Courtyard

Future home of classrooms, administration, and advising for:

  • UC Davis Extension Center for International Education
  • Global Affairs
    • Office of the Vice Provost
    • Services for International Students and Scholars
    • UC Davis Study Abroad

UC Davis is committed to extending its recognition as a leading international university. To achieve this vision, the campus is building a new international facility that will accommodate UC Davis Extension Center for International Education and Global Affairs (Office of the Vice Provost, Services for International Students and Scholars and UC Davis Study Abroad). These units are currently located in different campus and off campus locations. Placing these units within the same building will facilitate collaboration, communication and sharing of resources as well as consolidating services for both international students and students wishing to travel abroad.

The new building will provide classrooms, administrative spaces, a 3,400 square foot Commons area and other shared resources for the campus international programs.  The facility will centralize the international programs, promoting collaboration and creating a presence for an “international center” on Campus.

Supplemental content

Project Details

Project Manager

Vanda Rovis

vprovis@ucdavis.edu

(530) 754-1070

Project Coordinator

Karen Glover

kglover@ucdavis.edu

(530) 752-7197

Design Build Team Leads

Flint Builders, Inc.

MFDB Architects

Project Size

58,557 gross square feet

38,476 assignable square feet

Project Budget

$29,901,000

Completion Date

Fall 2016

Project Status

100% Construction Documents for Underground Civil was approved on 9/11/2014;  Notice to Proceed for mobilization and construction for underground civil was issued on 9/17/2014.  The underground civil work is currently ongoing on the project site.  We anticipate the 100% Structural package to be issued and approved by December 2014 allowing fabrication of steel to begin.  The remainder of the contract work will be issued in the 100% CD Construction package and is due in January 2015.